General Guidelines For Civil Engineering Works as described below by list

  1. In case of soil filling 100 sqm should take 3 samples for core cutting test.
  2. For constructional work PH value of work should not be less than 6.
  3. Water absorption of construction material should not be more than 15%.
  4. Reinforcement bar dia more than 36mm lap slices not to be used.
  5. Free open fall normal type of concrete not more than 1.5m.
  6. Minimum thickness of slabs 125mm.
  7. Main reinforcement bar for square column should not be less than 4 and should not be less than 6 for circular column.
  8. Reinforcement bar chairs minimum of 12mm diameter to be used.
  9. Diameter of dowel bar should be minimum 12mm.